Beckman LS6000 or LS6500 showing calendar failure
As of January 1st, 2021, the internal clock chip used in the Beckman Coulter LS 6000 and LS 6500 turned over to 1921. This chip is used to calculate the DPM of your sample as well as the print the date of the run. It did not have any data past the last day of 2020 causing it to roll over to 1921. If you are using your Beckman Liquid Scintillation Counter for DPM calculation or just need your results to show the correct date the samples were run Tritech has a patch to fix the problem. It will restore the correct date out to 2040. If you would like to have this patch added to your Beckman Counter Liquid Scintillation Counter please call our service department for a quote. Office 410.798.7610 or email us at admin@tritechinc.com

2 Comments
Dear Tritch,
We would like to have the patch installed on our Beckman LS6500 to yield dpm and correct date.
Thank you
We have a Beckman LS6000 with the date problem you describe. We would like a quote for the patch to fix this date problem.